Project Updates

On April 25, 2017, hospital district residents voted to approve a bond to help fund construction of a new hospital facility in Chelan. The new building (rough architect’s rendition above) will have private patient rooms, larger birthing rooms, increased outpatient capacity and a bigger emergency room. It will also have space for rehabilitative therapy, laboratory and radiology, as well as an expanded surgery department and a helicopter pad for emergency transfers. The fully ADA accessible hospital will be designed for cost effectiveness.

The new building will be built on hospital-owned property at Chelan Apple Blossom Drive, near Wal-Mart, across from the new Columbia Valley Community Health Clinic construction.

The cost of the construction project is $44.5 million. Voters voted to pay $20 million. The remaining costs will be funded by the hospital, grants and the LCCH Foundation.

The hospital Board of Commissioners and administration worked with outside financial and healthcare consultants to explore facility options. Multiple community meetings were held to gather input in 2016 and 2017. The building project is based on the results of those reports and meetings.

September 2017 Update
Lake Chelan Community Hospital & Clinics (LCCHC) had a terrific response to the request for proposals from general contractors, says Kevin Abel, LCCHC CEO. The organization received proposals from nine major contracting firms and is now in the review process.

August 2017 Update
The USDA grant application has been submitted. Over 15 contractors attended an informational meeting about the new hospital project Aug. 22. They met with General Contractor / Construction Manager (GC/CM) selection team: GC/CM consultant Dick Bratton, LCCH CEO Kevin Abel, LCCH Board Chair Mary Signorelli, project manager Barry Leahy & LCCH board member Phyllis Gleasman.

July 31, 2017 Update:
The State Project Review Committee unanimously approved the proposal by Lake Chelan Community Hospital & Clinics (LCCHC) to use the Construction Manager / General Contractor (GC/CM) building method for the new hospital facility last Thursday, July 27 after they heard an hour-long presentation by the LCCHC team. CLICK HERE FOR PRESS RELEASE

June 1 Update: We are currently in the process of applying to use the Construction Manager / General Contractor (GC/CM) method for the new hospital facility. With overlapping design and construction phases, this collaborative method incorporates the contractor’s point of view into the project much sooner than design-bid-build. The contractor is hired early enough to contribute expertise and order materials much earlier. Early inclusion of the contractor also helps the design phase transition seamlessly into the construction phase. Other GC/CM benefits include better budget control and time savings.

May 2017 Update: We are currently in the financing phase of the project, working with the USDA and other financial consultants. Our architect is CollinsWoerman in Seattle. There will be one year of planning and permitting and two years of construction.

REPORTS

Master Planning June 2

Minutes from June 14 Special Facility Planning Meeting